Risk Prevention Measures
I.Maintaining Site Security
Prior to leaving the construction site ensure that the project is secure as possible:
- Arranging permanent security guards to carry out construction site supervision
- If permanent security personnel cannot be provided, consider installing a video monitoring system (CCTV System) to detect and alert in the event of intrusion, vandalism, theft and fire
II.Safe Storage of Materials
- Consider temporarily removing valuable building materials to a secure area if possible
- Secure all packaging and materials that could be adversely impacted by weather (i.e. high winds, rain, storm).
3.Remove, secure, isolate or neutralize chemicals to prevent their release or their reaction together if disturbed. Ensure all flammable liquids and gases are removed from the site where appropriate.
4.To mitigate the risk of a fire loss, consider removing from the construction areas prior to vacating the site all paper and other combustible materials (wood, sawdust, trash, etc.).
III.Mitigating Losses From Equipment and Machinery
It is critical that equipment and machinery are protected in the event of work stoppage.
- For equipment not yet available on site, consider delaying the delivery of equipment to the jobsite until the project is resumed.
2.For equipment already onsite
- Classification and assessment of machinery affected by each type of weather (rain/wind/sun/flood/humidity) to arrange arrangement at an appropriate location in the construction site. For equipment that cannot be moved, appropriate protective measures should be taken (Ex: cover the equipment with fire-resistive covers or suitable sheeting for added protection)
- Address the most critical equipment first when defining priorities for loss prevention measures. Measures of criticality include potential damage and potential delay (lead time of spares).
IV.Make Partially Completed Work/Temporary Structures Safe
- 1.If possible complete portions of the work in such a way as to reduce rework and losses when the project resumes.
- For example, complete concrete placements to prevent cold joints; finish mud slabs as a means to cutoff water from below foundations; complete temporary roof structures to prevent water damage; and complete/ or secure structural frames to prevent instability.
- Prior to leaving the site, consider having a structural engineer perform a visual inspection of works, evaluating the potential stoppage period.
V. Mitigating Natural Hazard Risk
A stoppage could expose the project to seasonal events which were not anticipated, such as heavy rain, wind storm, flood, etc.
- Consider the consequences of these events on the uncompleted works and a full inspection of the worksite to prevent the risk of water intrusion
- Excavations and trenches also pose risks. Consider adjusting the slope of excavation to prevent sloughing/collapse from heavy rainfall while deep excavations should be protected to prevent water infiltration resulting in geotechnical instability. If needed, consider refilling trenches to avoid the risk of collapse with damage to existing cables and pipelines
VI.Mitigating Loss Potential When Restarting The Project
Consider what testing and inspections may be required prior to restarting the project
- When recommissioning, inspect the condition of MEP systems (electrical, water and gas systems) prior to energizing or pressurizing
- Have all engineering disciplines (structural, mechanical, electrical, geotechnical, etc.) inspect their respective works prior to resuming construction to confirm the project integrity.